Team 1 Issues and Recommendations

Back to the complete list of Issues

Issue discussed was: Many fields have limited wellhead and flow rate instrumentation. The lack of measurement data at each well means operators must often use rate estimation techniques for the purpose of reservoir management, engineering and production allocation. For example, if every well in a gathering system does not have a flow rate meter but is tested twice a year, the well test rates are used as an estimate for production allocation from the sales meter. This lack of instrumentation can lead to disagreements over the accuracy of production numbers.

Affinity Diagram for Team 1.
Affinity Diagram for Team 1.

Team 2 Results
Team 3 Results
Team 4a Results
Team 4b Results
Team 5 Results

Unless otherwise stated, the content of this page is licensed under Creative Commons Attribution-ShareAlike 3.0 License